MY KOLKATA EDUGRAPH
ADVERTISEMENT
regular-article-logo Monday, 23 December 2024

Uttarakhand: Rescue operations to evacuate 41 workers trapped in Silkyara tunnel enter final stretch

The drilling of 800 mm diameter steel pipes was halted for some hours overnight after an iron mesh came in the way of the auger machine

PTI Uttarkashi Published 23.11.23, 09:20 AM
Preperations underway near the Silkayara tunnel where rescue operation of 41 workers trapped inside the tunnel is underway, in Uttarkashi district.

Preperations underway near the Silkayara tunnel where rescue operation of 41 workers trapped inside the tunnel is underway, in Uttarkashi district. PTI

Rescue operations to evacuate 41 workers trapped in Uttarakhand's Silkyara tunnel entered the final stretch early Thursday after a late night hitch when the machine drilling the escape passage through the rubble hit a hard obstacle.

The drilling of 800 mm diameter steel pipes was halted for some hours overnight after an iron mesh came in the way of the auger machine, officials said.

ADVERTISEMENT

The last pipe to prepare the escape passage for the trapped workers was being pushed in through the rubble, an electrician working at the site said on Thursday morning.

All arrangements have been made to provide immediate medical care to the 41 trapped workers after they are evacuated, officials said.

A 41-bed separate ward has been readied at the Community Health Centre in Chinyalisaur for Silkyara tunnel evacuees and 41 ambulances wait outside the tunnel to rush them there as soon as they crawl out.

Till 6 pm on Wednesday, up to 44 metres of the escape pipe had been inserted into the debris, an official update said in Delhi.

Earlier, officials said the American-made auger machine had to drill through a 57-metre stretch of debris to reach the 41 workers, who were trapped when a portion of the under-construction tunnel collapsed 11 days ago.

The drilling from the Silkyara end was put on hold on Friday afternoon when the auger machine encountered a hard obstacle around the 22-metre mark, creating vibrations in the tunnel that caused safety concerns.

The drilling resumed around midnight Tuesday.

As the machine drills through, six-metre sections of steel pipes, just under a metre wide, are pushed into the escape passage. Once the pipeway reaches the other end, the trapped workers are expected to crawl out.

Except for the headline, this story has not been edited by The Telegraph Online staff and has been published from a syndicated feed.

Follow us on:
ADVERTISEMENT
ADVERTISEMENT