MY KOLKATA EDUGRAPH
ADVERTISEMENT
photo-article-logo Tuesday, 05 November 2024

In landslide-hit Wayanad, Indian Army Madras Engineers Group builds 190-foot bridge in 16 hours

Search and rescue operations that got underway on the early morning of August 2 received an impetus due to the completion of the Bailey bridge that will enable the movement of heavy machinery, including excavators, and ambulances to the worst-affected Mundakkai and Chooralmala hamlet

Our Web Desk Published 02.08.24, 01:36 PM

Indian Army’s Madras Engineers Group led by Major Seeta Shelke battled inclement weather in landslide-hit Wayanad in Kerala and built a 190-foot bridge with 24 ton capacity in just 16 hours. The construction of the bridge began early morning in July 31 and was finished by 5:30 pm on August 1. 

A Bailey bridge being constructed after landslides triggered by heavy rain at Chooralmala, in Wayanad district, Wednesday, July 31, 2024
1 7

A Bailey bridge being constructed after landslides triggered by heavy rain at Chooralmala, in Wayanad district, Wednesday, July 31, 2024

PTI
ADVERTISEMENT

Army engineers scrambled to construct the bridge to ferry heavy equipment from the nearest town of Chooralmala to the affected area, Mundakkai, after rising water in a river washed away a makeshift bridge on Wednesday. 

Construction of the bailey bridge on the morning of July 31
2 7

Construction of the bailey bridge on the morning of July 31

PTI

The main bridge was washed away in the landslides on Tuesday, leaving Mundakkai marooned. The disaster was the worst in Kerala since the deadly floods of 2018. Experts said the area had received heavy rain in the last two weeks that softened the soil before extremely heavy rainfall on Monday triggered the landslides. 

Reconstruction of Bailey bridge underway, that connects Mundakkai and Chooralmala and was washed away in the landslides triggered by heavy rain in the hilly areas of Wayanad district, July 31, 2024
3 7

Reconstruction of Bailey bridge underway, that connects Mundakkai and Chooralmala and was washed away in the landslides triggered by heavy rain in the hilly areas of Wayanad district, July 31, 2024

PTI

Although the bridge was supposed to be completed by 12 noon of August 1, heavy rainfall made it immensely difficult for the army to work.The bridge is built with a pier in the middle of the river due to its length.

The reconstructed bridge
4 7

The reconstructed bridge

X/@DefencePROTvm

The materials for the construction of the bridge were transported to Chooralmala from Delhi and Bengaluru. 

5 7
X/@DefencePROTvm

Lauding the army's efforts of building the bridge in record time, the defence spokesperson, Trivandrum, wrote on X: "Kudos to Maj Seeta Shelke & her team of Madras Engineers Group of Indian Army, who went beyond all kind of challenges & built  the 190 ft long bridge with 24 Ton capacity in 16 hours in Wayanad Started at 9 pm on 31 July & completed at 5:30 pm on 1 Aug."

6 7
X/@major_madhan

The Southern Command of the Indian Army also hailed the force for completing the daunting task, despite the adverse weather conditions and restricted time.

"Inclement weather, raising water levels, debris, restricted space seems like a daunting task for rescue for many but not for #IndianArmy. Madras Sappers displaying indomitable spirit, never say die attitude and supreme commitment in the relief operations completed 190ft Bailey Bridge in a record time and facilitated furtherance of rescue operations. Kudos to IndianArmy and the valiant Thambis working day and night in times of adversity," it wrote on X

7 7
X/@major_madhan

The army’s effort and work garnered praise on the internet with netizens congratulating them for their valour and for overcoming the adverse rage of nature and building the bridge in such a short time. 

Follow us on:
ADVERTISEMENT

MORE IN PICTURES

Share this article

CLOSE