MY KOLKATA EDUGRAPH
ADVERTISEMENT
regular-article-logo Wednesday, 03 July 2024

‘Urja Ganga’ gas pipeline delayed by nine months: GAIL India

The 3,306-kilometre Jagdishpur-Haldia-Bokaro-Dhamra pipeline was originally targeted for completion by June 2024

PTI New Delhi Published 01.07.24, 09:00 AM
Representational image

Representational image File picture

The construction of the 12,940-crore ‘Urja Ganga’ gas pipeline, India’s most ambitious project taking environment-friendly fuel to eastern parts of the country, has been delayed by nine months and will now be completed by March 2025, state-owned GAIL (India) Ltd said.

The 3,306-kilometre Jagdishpur-Haldia-Bokaro-Dhamra pipeline was originally targeted for completion by June 2024.

ADVERTISEMENT

But due to “delay in right of use (RoU) availability”, the completion schedule has been revised “from June 2024 to March 2025”, GAIL said in a stock exchange filing.

The bulk of the pipeline has already been constructed, and gas has started to flow in most cities along the route.

Traditionally, natural gas was available for use as fuel to generate electricity, make fertiliser or turn into CNG and cooking gas only in the western and northern parts of the country, as pipelines taking the fuel from source to users were limited to these parts.

In October 2016, work on laying a pipeline from Jagdishpur in Uttar Pradesh to Haldia in Bengal, Bokaro in Jharkhand and Dhamra in Odisha began.

The line was extended to Guwahati in Assam from Barauni in Bihar, a length of 726 km, to take the fuel to hereto-unconnected states in the eastern region.

The Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL), popularly called the Pradhan Mantri Urja Ganga pipeline, is to supply gas to the eastern states of Bihar, Jharkhand, Odisha and Bengal.

GAIL, the firm executing the pipeline, said its board of directors in a meeting on June 28 approved the revision of the completion schedule.

The completion schedule for the 240-km Dhamra-Haldia pipeline has also been revised from June 2024 to March 2025, it added.

The company on May 10, 2019, stated that it has completed awards of all major contracts worth 10,500 crore for pipeline supply and laying of the integrated 3400-km Jagdishpur-Haldia and Bokaro-Dhamra Natural Gas Pipeline (JHBDPL) and Barauni-Guwahati Pipeline (BGPL) pipeline.

The government provided 40 per cent viability gap funding amounting to 5,176 crore for execution of JHBDPL.

For the Barauni-Guwahati pipeline, a 60 per cent viability gap funding, amounting to 5,559 crore, has been provided by the government.

PTI

Follow us on:
ADVERTISEMENT